Or ribbonblock as I first heard it! This is what our slab first floor roof is made up of. Quite an interesting procedure. They order premade long lengths of reinforced concrete ribs, which are laid on the brick work at first floor level. Then into that they drop specially made blocks that wedge into the ribs. These things all weigh a ton - it is quite scary to think about the weight of the roof just above our heads. But, as my mom said, dad isn't worried, the builder, Esrom isn't worried, so nor will I. We might just be like chicken licken for a while worrying about the roof falling on our heads!
This is how the ribs look:
Then they put the blocks in between. This is what it looks like from below. The support structures apparently have to stay in place for 2 weeks.
The wood at the front of the house forms a structural beam across the front of the patio. We have others elsewhere but this is easy to see. They make a box out of wood, put steel reinforcing inside, and then when the first floor slab is laid, it gets filled with concrete and forms an incredible strong beam. Please admire our pillars at the front of the patio. They are erected as hollow pillars, and they too get filled with concrete and steel. This house is surely going to stand for a loooong time!!
I braved it up the ladder to the first floor and this is how it looks from above. Next step is to pour the 100mm slab of concrete on top of this. There was a mad scurry of builders, electricians and plumbers to get all their piping laid before the slab went down.